Questions # 301:

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

Options:

A.

Arrange a team-building activity to foster understanding and open communication among the team members.


B.

Allow the team members to continue using their preferred communication tools and methods.


C.

Initiate a conversation with the team members individually to understand their situations regarding communication.


D.

Instruct the team members to adapt to the project's communication tools and methods.


Expert Solution
Questions # 302:

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

Options:

A.

Propose to close the project because it no longer fits the business values of the organization.


B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.


C.

Calculate float on the project because it has severely affected the project's major critical path.


D.

Request additional resources from the business unit manager due to the project's complexity.


Expert Solution
Questions # 303:

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?

Options:

A.

Ask the product owner to update the stakeholders' contact information at every meeting to address any changes.


B.

Update the stakeholder's information and inform them that they must make the team aware of any changes.


C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.


D.

Check the stakeholder register and ensure that every stakeholder's information is correct and current.


Expert Solution
Questions # 304:

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

Options:

A.

Risk to delivery


B.

Technical complexity


C.

Business value


D.

Estimation accuracy


Expert Solution
Questions # 305:

A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?

Options:

A.

Provide the HR review team with the team norms document.


B.

Invite the HR review team to attend one of the daily standup meetings.


C.

Discuss the resource management plan with the HR review team.


D.

Direct the HR review team to the communications management plan.


Expert Solution
Questions # 306:

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

Options:

A.

Escalate the issue of the additional requirements to the executive leadership team.


B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).


C.

Implement all the requirements the customer has requested.


D.

Adjust the scope baseline and schedule baseline accordingly.


Expert Solution
Questions # 307:

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

Options:

A.

Discuss this issue with the affected team members and support them during the transition.


B.

Start looking for replacements as soon as possible to help prevent any schedule slippage.


C.

Engage with the project sponsor to ensure that this change does not affect the project execution.


D.

Determine the impact to the project and implement mitigations per the project management plan.


Expert Solution
Questions # 308:

A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.

What should the project manager do next?

Options:

A.

Discuss the issue with the team member in a one-on-one meeting.


B.

Ask the team member to justify the delay during a team meeting.


C.

Review the human resources (HR) policies for relevant corrective actions.


D.

Escalate the performance issue to the team member's functional manager.


Expert Solution
Questions # 309:

A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project

team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.

What should the project manager do?

Options:

A.

Discuss with the team, estimate the effort, and raise a change request.


B.

Discuss with the customer the risks identified and team's concerns.


C.

Ask the team to deliver the functionality on the agreed go-live date.


D.

Ask the customer to go live and add the new functionality in the backlog.


Expert Solution
Questions # 310:

After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?

Options:

A.

Speak with the project sponsor to find out if the stakeholder would agree to a one-on-one review session


B.

Log the stakeholder's comments in the risk register as a high-impact threat to the project's completion


C.

Consider the stakeholder's concerns and review the project charter with the project sponsor.


D.

Note the stakeholder's concerns but disregard them with regard to the project activities.


Expert Solution
Questions # 311:

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?

Options:

A.

Ensure team B prioritizes the dependent activity in iteration three.


B.

Include the dependent activity in the current iteration for team B.


C.

Assign the two critical activities to team B in iteration two.


D.

Cancel the current iteration and reschedule it with the dependent activity.


Expert Solution
Questions # 312:

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

Options:

A.

Help the team members by organizing regular stress-relieving and team- building sessions.


B.

Request additional resources to continue delivering value while reducing team stress.


C.

Support the team during the planning phase to only commit to what they are able to deliver.


D.

Ask individual team members to plan staggered leave to avoid becoming stressed.


Expert Solution
Questions # 313:

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

Options:

A.

Follow the requirements management process.


B.

Follow the stakeholder engagement process.


C.

Follow the risk management process.


D.

Follow the change management process.


Expert Solution
Questions # 314:

During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.

What should the project manager do?

Options:

A.

Ensure a continuous feedback environment is leveraged to improve the quality and overall satisfaction.


B.

Review the requirements and instruct the team to develop the deliverables according to the documentation.


C.

Mentor the team members and ensure they perform peer reviews of their work before implementation.


D.

Utilize the retrospectives to identify issues in the development phase that may cause deliverables to not be accepted.


Expert Solution
Questions # 315:

A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.

What should the project manager do?

Options:

A.

Meet with the project sponsor and key stakeholders to confirm that the information about the forecasted project value is accurate.


B.

Ask the organization to cancel the project because the project manager is unable to confirm that the project will deliver the forecasted value.


C.

Proceed with execution of the project whether the information about the forecasted value is right or not because the project is already approved.


D.

Develop scope alternatives to achieve the forecasted project value in the event that project benefits information is inaccurate.


Expert Solution
Questions # 316:

A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that

worked well for previous projects. However, a few team members are not happy with this plan.

What should the project manager have done to avoid this?

Options:

A.

Delegated the responsibility of selecting the collaboration tools to the project's technical lead.


B.

Met with the project team to determine their collaboration needs and identified tools that will work best.


C.

Allowed the project team members to use the tools that will work best for them for this project.


D.

Asked the project sponsor for approval to purchase the newest collaboration tool on the market.


Expert Solution
Questions # 317:

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

Options:

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.


B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.


C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.


D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.


Expert Solution
Questions # 318:

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?

Options:

A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.


B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.


C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.


D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.


Expert Solution
Questions # 319:

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.

Add 4 additional weeks to the schedule and request additional resources.


B.

Ask the sponsor to obtain a special work permit to continue work.


C.

Review the project management plan to see the impact of the possible delay.


D.

Crash the resource management plan to keep the schedule on track.


Expert Solution
Questions # 320:

A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?

Options:

A.

Reject the request as being too late and leading to major scope creep.


B.

Submit the request to the change control board (CCB) for a decision.


C.

Negotiate with the project sponsor on the possible alternatives.


D.

Determine the possible impact of this change on all aspects of the project.


Expert Solution
Questions # 321:

A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?

Options:

A.

Divide the allocated budget by the number of work packages and verify that each work package can be completed within the allocated budget.


B.

Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.


C.

Create a budget burndown and a scope burnup and then verify that the project scope is completed before the allocated budget is depleted.


D.

Fund each work package in the order of its importance and shift any remaining scope from nonfunded work packages to funded work packages.


Expert Solution
Questions # 322:

A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?

Options:

A.

Accept the situation knowing there is schedule slack available to release on an incremental basis when necessary.


B.

Call each team member to gain their perspective on the problem, then bring the whole team together to discuss a solution.


C.

Send each team member a direct email indicating that disciplinary action is likely if they do not change their attitude.


D.

Contact the project sponsor to request approval to release the current team and hire replacement personnel.


Expert Solution
Questions # 323:

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.


B.

Meet with the client to discuss the issue with the subcontractor.


C.

Inform the subcontractor that they must send the schedule.


D.

Tell the subcontractor to submit a draft schedule.


Expert Solution
Questions # 324:

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

    Update the issue log and refer to the resource management plan to address the situation.

    Ask the team for extra work to fulfill the project commitment.

    Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.


Expert Solution
Questions # 325:

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

Options:

A.

Review the project schedule and ask for the contingency reserve to crash the project.


B.

Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.


C.

Review the lessons learned register with the former project manager in a private meeting.


D.

Meet the project team to assert authority and reassign the project tasks for a timely delivery.


Expert Solution
Questions # 326:

A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?

Options:

A.

Developed a detailed, phased procurement management plan including all activities required and had the client approve it.


B.

Included the client in all negotiation phases with the consultancy to obtain their advanced approval before signing the contract.


C.

Prepared and negotiated a second contract with the consultancy firm for the remaining 14 months after the first contract signature.


D.

Agreed beforehand with the client on the frequency of reporting on the status of the procurement activities within the project.


Expert Solution
Questions # 327:

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two

projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.

What kind of leadership style should the project manager utilize for the current project?

Options:

A.

Transformational


B.

Interactional


C.

Laissez-faire


D.

Charismatic


Expert Solution
Questions # 328:

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?

Options:

A.

Evaluate the impact of nonrenewal of the license.


B.

Escalate the licensing issue to the product owner.


C.

Add a spike to the backlog for an alternative design.


D.

Raise a change request to secure the renewal.


Expert Solution
Questions # 329:

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.

Lessons learned database


B.

Procurement strategy


C.

Vendor's website


D.

Appropriate financial regulations


Expert Solution
Questions # 330:

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?

Options:

A.

Apply appropriate conflict resolution techniques to solve the issue.


B.

Call a team meeting to have a formal discussion of the issue.


C.

Allow the team to work through it on their own unless help is needed.


D.

Engage in individual conversation with each team member.


Expert Solution
Questions # 331:

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?

Options:

A.

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.


B.

Include the project stakeholders’ needs while planning the project communications strategy.


C.

Designate a team member to respond to the emails from these stakeholders.


D.

Include the stakeholders’ emails in all of the project status communications.


Expert Solution
Questions # 332:

A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?

Options:

A.

Send a detailed email with the completed design document.


B.

Conduct a workshop with all of the stakeholders.


C.

Conduct a workshop with both of the teams.


D.

Upload the design documents into the project repository.


Expert Solution
Questions # 333:

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

Options:

A.

Counsel both team members and caution them with a final warning.


B.

Escalate the issue to the human resources (HR) manager before a larger problem develops.


C.

Help cultivate self-awareness between the two team members through emotional intelligence (El).


D.

Relocate the two project team members into different project teams.


Expert Solution
Questions # 334:

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

Options:

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.


B.

Review the terms of reference of the steering committee to include the vendor management head.


C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.


D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.


Expert Solution
Questions # 335:

A project manager is preparing a budget estimation for an international construction project. They decide to consult the project team members who are experienced in this type of project and are familiar with the local laws of the country.

Which budgeting approach would be the least risky for the project team to apply?

Options:

A.

Review historical data and provide parametric estimations for the activities, including local law restrictions.


B.

Use a top-down estimation and add contingencies to cover any future impacts regarding the legal context.


C.

Make a general estimation using a standard legal approach and then look to include early definitions.


D.

Discuss and compile the local information about laws to develop bottom-up estimations.


Expert Solution
Questions # 336:

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.

What should the project lead do?

Options:

A.

Ask that estimations be provided only by senior developers.


B.

Allocate more time for estimation in the sprint planning.


C.

Review and update the estimations in the daily standup.


D.

Recommend a different estimation method in the retrospective.


Expert Solution
Questions # 337:

A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?

Options:

A.

The project sponsor should select the project artifacts that the project manager and project management team should use in the project.


B.

The project manager and project management team should use the standard project artifacts from the database.


C.

The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.


D.

The project manager and the project management team should select the appropriate artifacts for use in the specific project.


Expert Solution
Questions # 338:

A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts

with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high

performer, the project goals may be negatively impacted if they leave the team.

What should the project manager do in this situation?

Options:

A.

Meet with the developer and ask them to be respectful with the other team members and work together as a team.


B.

Meet with the team members and developer individually to understand the situation and build an action plan accordingly.


C.

Collect the team's feedback and send it to human resources (HR) to resolve the conflict.


D.

Arrange a team-building training session and require all of the team members to attend.


Expert Solution
Questions # 339:

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

Options:

A.

Develop different approaches based on team members’ motivation and ability.


B.

Develop a standard approach to provide feedback to all team members.


C.

Provide intensive oversight to the team members who performed poorly.


D.

Create a new standard performance measure based on project requirements.


Expert Solution
Questions # 340:

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

Options:

A.

Measure the team's psychological safety.


B.

Reschedule the team's retrospective meeting.


C.

Coach the team to be more inclusive.


D.

Rotate the team's daily meeting roles frequently.


Expert Solution
Questions # 341:

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate most authorities and control the authority by withholding important information.


B.

Delegate certain authorities and control the authority by withholding important information.


C.

Delegate certain authorities and share information to allow fair decision-making.


D.

Delegate most authorities and share information to allow fair decision-making.


Expert Solution
Questions # 342:

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

Options:

A.

Escalate the issue to the change control board (CCB).


B.

Ask the project team to analyze the impact.


C.

Register the risk and document the contingency plan.


D.

Have the project team brainstorm alternatives.


Expert Solution
Questions # 343:

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the Scrum team members to share retrospectives.


B.

Ask the scrum master to attend the workshops.


C.

Invite the Scrum team members as optional participants.


D.

Invite the Scrum team members as mandatory participants.


Expert Solution
Questions # 344:

During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?

Options:

A.

Assign the work based on the skill sets of team members.


B.

Request feedback from stakeholders about the quality delivery.


C.

Assign the work in consultation with the functional manager.


D.

Discuss this with the team and review the quality process.


Expert Solution
Questions # 345:

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for

several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?

Options:

A.

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.


B.

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.


C.

Review the contract with the vendor to go over the financial penalty that is applicable to this situation.


D.

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.


Expert Solution
Questions # 346:

The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)

Options:

A.

Leverage the project governance system to track and manage the project artifacts.


B.

Create a central repository system to assess the effectiveness of the project artifacts.


C.

Review the execution roadmap and ask the legal team to manage the artifacts.


D.

Ensure the project artifacts are kept up to date and accessible to all stakeholders.


E.

Work with the team to determine the process to manage the project artifacts.


Expert Solution
Questions # 347:

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

Options:

A.

Schedule a lessons learned meeting with the project team and close out the project.


B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.


C.

Prepare a transition plan to hand over the operations and other closing documentation.


D.

Document the project manager's departure and the missing documents in the risk log.


Expert Solution
Questions # 348:

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

Options:

A.

Use the project budget and procure a new server before raising a change request.


B.

Request that the requirement is funded with the business operational expenses.


C.

Apply contingency reserves to procure a server that fits the requirement.


D.

Raise a change request and obtain approval from the project owner.


Expert Solution
Questions # 349:

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office

(PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

Options:

A.

Engage key stakeholders to complete and deliver lessons learned.


B.

Select the same stakeholders for the next project to avoid doing knowledge transfer.


C.

Present the project achievements and delegate knowledge transfer to the steering committee.


D.

Request the PMO to manage the lessons learned repository.


Expert Solution
Questions # 350:

A project manager holds periodic progress review meetings to discuss issues. What should the project manager do first on the agenda?

Options:

A.

Produce lessons learned documentation.


B.

Elaborate the risk mitigation strategy and risk register.


C.

Formulate project management plan integration.


D.

Update resolution approaches and action assignments.


Expert Solution