Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 322 Topic 33 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 322 Topic 33 Discussion

PMP Exam Topic 33 Question 322 Discussion:
Question #: 322
Topic #: 33

Shipping problems are impacting the supply chain worldwide, and the project's primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?


A.

Note the information but refrain from recording it as an issue because the project has not yet placed the order.


B.

Request the procurement team to find another vendor that has available stock of this equipment.


C.

Update the risk and continue to monitor developments by keeping in touch with the vendor.


D.

Request the vendor to provide specific information about the delivery delays before taking any action.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.