PMI Project Management Professional (2025 Version) PMP Question # 322 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 322 Topic 33 Discussion

PMP Exam Topic 33 Question 322 Discussion:
Question #: 322
Topic #: 33

A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?


A.

Accept the situation knowing there is schedule slack available to release on an incremental basis when necessary.


B.

Call each team member to gain their perspective on the problem, then bring the whole team together to discuss a solution.


C.

Send each team member a direct email indicating that disciplinary action is likely if they do not change their attitude.


D.

Contact the project sponsor to request approval to release the current team and hire replacement personnel.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.