Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 322 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 322 Topic 33 Discussion

PMP Exam Topic 33 Question 322 Discussion:
Question #: 322
Topic #: 33

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?


A.

Assess the impact of the features and refer it to the change control board (CCB).


B.

Implement the new features after assessing the impact.


C.

Reject the new features since it amounts to gold plating.


D.

Add the new features to avoid losing the sponsor's support for the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.