Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 321 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 321 Topic 33 Discussion

PMP Exam Topic 33 Question 321 Discussion:
Question #: 321
Topic #: 33

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)


A.

Inform the customer that moving the milestone has a very high impact on project cost.


B.

Escalate the Issue to senior management so they can impose a solution on the customer.


C.

Convince the customer to keep the requirements as is and not move the milestone.


D.

Review the customer's priorities regarding the desired requirements for the milestones.


E.

Discuss which requirements can be delivered faster with the project team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.