Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 321 Topic 33 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 321 Topic 33 Discussion

PMP Exam Topic 33 Question 321 Discussion:
Question #: 321
Topic #: 33

Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?


A.

Begin daily check-ins with the two vendors to recover time at their own expense


B.

Extend the project schedule and inform the vendors it was due to their poor performance


C.

Find replacements for the two vendors to complete the project in a timely manner


D.

Reduce the two vendors’ pay due to poor performance and lack of communication


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.