PMI Project Management Professional (2025 Version) PMP Question # 321 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 321 Topic 33 Discussion

PMP Exam Topic 33 Question 321 Discussion:
Question #: 321
Topic #: 33

A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?


A.

Divide the allocated budget by the number of work packages and verify that each work package can be completed within the allocated budget.


B.

Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.


C.

Create a budget burndown and a scope burnup and then verify that the project scope is completed before the allocated budget is depleted.


D.

Fund each work package in the order of its importance and shift any remaining scope from nonfunded work packages to funded work packages.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.