Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 320 Topic 33 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 320 Topic 33 Discussion

PMP Exam Topic 33 Question 320 Discussion:
Question #: 320
Topic #: 33

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?


A.

Find another vendor to deliver the required supplies on time


B.

Ask the procurement manager to resolve the issue with the vendor


C.

Document this as a risk and define a risk response plan


D.

Treat the risk as an issue and launch the risk response plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.