PMI Project Management Professional (2025 Version) PMP Question # 320 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 320 Topic 33 Discussion

PMP Exam Topic 33 Question 320 Discussion:
Question #: 320
Topic #: 33

A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?


A.

Reject the request as being too late and leading to major scope creep.


B.

Submit the request to the change control board (CCB) for a decision.


C.

Negotiate with the project sponsor on the possible alternatives.


D.

Determine the possible impact of this change on all aspects of the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.