Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 320 Topic 33 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 320 Topic 33 Discussion

PMP Exam Topic 33 Question 320 Discussion:
Question #: 320
Topic #: 33

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?


A.

Refer to the project charter


B.

Review the project resource matrix


C.

Assess the stakeholder register


D.

Update the communications management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.