A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?
The project charter is a document that formally authorizes a project or a phase and documents initial requirements that satisfy the stakeholder’s needs and expectations. It provides the project manager with the authority to apply organizational resources to project activities. When a new project manager is assigned to a project, they should refer to the project charter to understand the project objectives, key stakeholders, risks, and the authority delegated to them. References: Project Management Professional (PMP) Reference Materials12.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit