Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 1 out of 13 pages
Viewing questions 1-50 out of questions
Questions # 1:

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field


B.

Team members, engineers, and weather experts


C.

Team members, consultants from outside the project with experience in the field, and the customer


D.

Weather experts, functional managers, and team members


Expert Solution
Questions # 2:

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.


B.

Organize a stakeholder meeting to brainstorm on general project risks.


C.

Extract this from the project risk register tracking tool and issues log.


D.

Refer the sponsor to the contract document.


Expert Solution
Questions # 3:

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.

Independent personal testing


B.

Security and performance testing


C.

An experimental approach to cover all possible choices


D.

Story testing


E.

Tests based on behavior and test-driven development


Expert Solution
Questions # 4:

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

Options:

A.

Coach those team members lacking hybrid knowledge to learn on the job.


B.

Change the team to include hybrid experts


C.

Assess the required training per team member.


D.

Deliver hybrid training to all team members


Expert Solution
Questions # 5:

Match the project situation on the left to the meeting on the right where the situation could occur.

Question # 5


Expert Solution
Questions # 6:

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor's approval to extend the project schedule.


B.

Set up a meeting to perform a root cause analysis.


C.

Update the issue log and communicate it to the team.


D.

Permanently colocate the team for better performance.


Expert Solution
Questions # 7:

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?

Options:

A.

Perform quality control analysis.


B.

Perform root cause analysis (RCA).


C.

Perform trend analysis.


D.

Perform schedule analysis.


Expert Solution
Questions # 8:

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

Options:

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.


B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.


C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.


D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.


Expert Solution
Questions # 9:

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.


B.

Emphasize the adoption of a predictive approach to minimize ambiguity.


C.

Recommend an agile approach so the project can be delivered iteratively.


D.

Outsource development of the product to a third party with more experience.


Expert Solution
Questions # 10:

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Options:

A.

Injury or loss incidents could delay project deliverables.


B.

It is imperative that established performance metrics are met.


C.

The project manager is obligated to comply with the project location's regulatoryrequirements.


D.

The project manager must follow their employer's organizational process assets(OPAs).


Expert Solution
Questions # 11:

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

Options:

A.

Emphasize the ground rules and then focus on today's activities and impediments.


B.

Let the discussion go on as it is important that the team is clear on priorities for theday.


C.

Address the team members involved during the next sprint retrospective.


D.

Avoid the discussion by referring to the team charter.


Expert Solution
Questions # 12:

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

Options:

A.

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.


B.

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.


C.

Request that the key resource's functional manager work directly with the resourceduring the project.


D.

Discuss this with the project sponsor and request that this key resource be replaced onthe project.


Expert Solution
Questions # 13:

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

Options:

A.

Add the stakeholder details into the periodic reports and update the project management plan


B.

Invite the stakeholder to all future project review meetings and update the project management plan


C.

Update the project management plan with the new information and inform all of the relevant stakeholders


D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan


Expert Solution
Questions # 14:

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

Options:

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.


B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country


C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.


D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.


Expert Solution
Questions # 15:

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

Options:

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.


B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.


C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.


D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.


Expert Solution
Questions # 16:

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Question # 16


Expert Solution
Questions # 17:

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.

Notify all team members that all steps in the process must be completed.


B.

Escalate the issue to the other executive leadership members.


C.

Schedule a review of the process steps with the team and the COO.


D.

Redesign the process so the team can move more quickly.


Expert Solution
Questions # 18:

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk


B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members


C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices


D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update


Expert Solution
Questions # 19:

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?

Options:

A.

Assessed and analyzed personality indicators from the project team


B.

Sent the activity details to everyone involved prior to the session


C.

Communicated the decision to conduct this activity to the key team stakeholders


D.

Selected a vendor for the activity according to the procurement management plan


Expert Solution
Questions # 20:

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.

Evaluate the possibility of managing this project using a predictive approach.


B.

Submit a change request for a new team that has agile experience.


C.

Mentor the team to explain agile principles and create a shared understanding.


D.

Hire a functional manager who is familiar with agile methodologies.


Expert Solution
Questions # 21:

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

Options:

A.

Set up a meeting with the stakeholder to address their concerns directly


B.

Move to a predictive design-and-requirements gathering approach


C.

Talk to the team separately to address the stakeholder's concerns


D.

Schedule a team retrospective and invite the stakeholder


Expert Solution
Questions # 22:

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.

Escalate the issue to the team member's functional manager and request a responseas soon as possible.


B.

Meet with the team member to understand what the issues are and to provide support.


C.

Leverage other team members who are contributing and making the project a success.


D.

Have the team member transferred to another project and add other resources to theproject.


Expert Solution
Questions # 23:

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

Options:

A.

Ensure full participation of both the product owner and business SMEs in scopeplanning sessions.


B.

Identify virtual communication methods and arrange for regular team meetingsaccordingly.


C.

Explore the opportunity to have both teams colocated.


D.

Plan for frequent face-to-face meetings.


Expert Solution
Questions # 24:

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

Options:

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.


B.

Establish a pull communications method to access knowledge repositories and lessons learned.


C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.


D.

Establish a push communications method for the team to share knowledge and lessons learned.


Expert Solution
Questions # 25:

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

Options:

A.

Use a servant leader approach.


B.

Assume the functional manager role.


C.

Perform the project sponsor activities.


D.

Act as the project owner.


Expert Solution
Questions # 26:

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

Options:

A.

Recommend agile training programs that best suit the client project manager's schedule.


B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.


C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals


D.

Provide the client project manager with agile best practice documents and web resources.


Expert Solution
Questions # 27:

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.

Identify how the proposed changes will benefit the project in relation to the businesscase.


B.

Ask for a temporary budget increase to avoid cost overruns.


C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.


D.

Assess the schedule delay and begin implementation to avoid additional lags


Expert Solution
Questions # 28:

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Options:

A.

Design a set of metrics including velocity, which is a good measure of value delivered.


B.

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)


C.

Promote a productive environment where everybody can work without interruptions from the rest of the team members


D.

Create a reward system recognizing group contributions to get people motivated and improve performance


Expert Solution
Questions # 29:

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

Options:

A.

Set up a requirements review session and obtain agreement for selection criteria.


B.

Recommend to the team to add the sponsor's preferred supplier to the list.


C.

Choose the sponsor's preferred supplier for the project to avoid conflict between theteam and sponsor.


D.

Recommend to the sponsor to review the results of the team's supplier evaluation.


Expert Solution
Questions # 30:

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.


B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.


C.

Replace the key team members with new resources who are already aware of the agilemindset.


D.

Provide directions to the team members on how to accelerate the company'stransformation, bringing the project back on track.


Expert Solution
Questions # 31:

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.


B.

Check social media to determine if there are any common connections that use the new supplier.


C.

Request assistance from the procurement department on the next steps.


D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.


Expert Solution
Questions # 32:

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Options:

A.

Recurrent team meetings are planned to control the budget against future uncertainties.


B.

Probabilistic analysis was used to develop the budget to address future uncertainties.


C.

The budget was developed by using the lessons learned from previous project data.


D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.


Expert Solution
Questions # 33:

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

Options:

A.

Ensured the project team documented lessons learned about the issue


B.

Ensured the project team applied a long-term solution for the issue


C.

Asked the project team to conduct more testing with users


D.

Discussed the issue with the stakeholders


Expert Solution
Questions # 34:

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.


B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.


C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.


D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.


Expert Solution
Questions # 35:

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.

Held a touchpoint with marketing before the demo to discuss any impediments


B.

Scheduled a demo presentation of the product during the first reason


C.

Asked the marketing team to start working on the product immediately


D.

Confirmed marketing requirements and constraints when adding to the backlog


Expert Solution
Questions # 36:

Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan


B.

Review the quality management plan


C.

Review the requirements traceability matrix


D.

Review the work breakdown structure (WBS)


Expert Solution
Questions # 37:

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

Options:

A.

Request a change in the contract in order to add the deliverable


B.

Add this deliverable to the requirements traceability matrix


C.

Terminate the contract and commence the closeout process


D.

Look to see if the deliverable is described in the statement of work (SOW)


Expert Solution
Questions # 38:

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.

Review the communications management plan with the team members.


B.

Remind the team members to follow the team charter.


C.

Motivate the team members to speak freely in the meeting.


D.

Arrange a team-building activity to involve all team members.


Expert Solution
Questions # 39:

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

Options:

A.

Evaluate the project exit criteria in the project charter.


B.

Reach out to the senior executive sponsor for the project.


C.

Understand the project success criteria and objectives.


D.

Review the project status reporting for the latest information.


Expert Solution
Questions # 40:

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.


B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.


C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.


D.

Meet with the team member and search for the root cause of their behavior.


Expert Solution
Questions # 41:

A project team that is very experienced in enterprise resource planning (ERP)

systems implementation is currently planning the delivery of a new ERP project. There is a

requirement to reuse the client's security subsystem developed by a third party. The client

states that integration with the security subsystem must be done by the client's team. The

project manager does not want to have such an external dependency.

What should the project manager do first?

Options:

A.

Plan the implementation of this integration in the first iteration to help reduce risks.


B.

Record the issue in the issue log and closely manage this dependency.


C.

Inform the client that the project team will take care of the integration.


D.

Document the client's responsibility for the integration with the security subsystem.


Expert Solution
Questions # 42:

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

Options:

A.

Request to meet with the team member and ask that any issues be escalated separately.


B.

Reprimand the team member and provide immediate coaching on goal alignment.


C.

Proceed with defining the goals with the team members given the majority approval from the team.


D.

Approach the team member with empathy and obtain agreement through collaboration.


Expert Solution
Questions # 43:

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.

Requirements analysis


B.

Retrospective


C.

Sprint planning


D.

Standup


E.

Backlog refinement


Expert Solution
Questions # 44:

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?

Options:

A.

Increase resources on the technical design to enable a decision to proceed as this is aquick return project.


B.

Increase the time spent on project development to improve the level of confidence tovalidate the financial evaluation.


C.

Conduct a stakeholder survey with the plant operators to establish the probability ofthis project reducing the cost of utilities.


D.

Stop any further project development and commence with the implementation as thereis no need to seek further approval.


Expert Solution
Questions # 45:

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Question # 45


Expert Solution
Questions # 46:

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.

Redefine the communications management plan


B.

Develop an integrated change management plan


C.

Document the risk in the project risk register


D.

Review the scope defined in the project charter


Expert Solution
Questions # 47:

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices


B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant


C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)


D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting


Expert Solution
Questions # 48:

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.


B.

Speak to the customer and add the issue to the issue log.


C.

Review user roles and update the team charter.


D.

Involve the product owner to rewrite the user stories.


Expert Solution
Questions # 49:

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.


B.

Meet with the client to discuss the issue with the subcontractor.


C.

Inform the subcontractor that they must send the schedule.


D.

Tell the subcontractor to submit a draft schedule.


Expert Solution
Questions # 50:

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.


B.

Email the team a detailed outline of the business requirements.


C.

Review the project charter with the team.


D.

Facilitate a discussion of the vision for the project.


Expert Solution
Viewing page 1 out of 13 pages
Viewing questions 1-50 out of questions