Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 1 out of 12 pages
Viewing questions 1-50 out of questions
Questions # 1:

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.

Follow the risk management plan.


B.

Reduce the team effort utilization.


C.

Look for cost-saving opportunities.


D.

Submit a change request to add to the management reserve.


Expert Solution
Questions # 2:

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.

Appoint a dedicated product manager for the duration of the release


B.

Have the customer approve the product increment features.


C.

Ensure every user story has acceptance criteria.


D.

Track business outcomes for planned user stories.


Expert Solution
Questions # 3:

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status


B.

Assign one person to be responsible for the task


C.

Establish a clear definition of done (DoD) for each task


D.

Encourage team members to work together


Expert Solution
Questions # 4:

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.


B.

Ensure that all team members complete the training.


C.

Redesign the training courseware to make it interesting.


D.

Retrain the team members responsible for the breaches.


Expert Solution
Questions # 5:

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

Options:

A.

Submit a change request to adapt the objectives of the project to the current situation


B.

Ask the scrum master to refine the user stones to improve the team members' understanding


C.

Find and provide training to the project team members who do not have the required skills


D.

Extend the duration of standup meetings to include skill transference from trained to untrained members


Expert Solution
Questions # 6:

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure


B.

Work breakdown structure (WBS)


C.

Team charter


D.

Project charter


Expert Solution
Questions # 7:

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone


B.

Delay sending a formal communication until the project team catches up


C.

Ask for a meeting with the sponsor to decide whether to send the formal communication


D.

Forego the formal communication and have a conversation with the supervisor


Expert Solution
Questions # 8:

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.


B.

Reconcile the team member to the key stakeholder's recommendation.


C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action


D.

Work with both the team member and the key stakeholder to reach a consensus.


Expert Solution
Questions # 9:

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.


B.

The team productivity is higher; therefore, more value is delivered,


C.

The cost is reduced: therefore, the total value delivered is higher.


D.

The risk is significantly reduced; therefore, more value Is delivered.


Expert Solution
Questions # 10:

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.


B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,


C.

Identify the technical requirements and request that management hire external resources,


D.

Document the problem in the issue log and suggest a change request to decrease the scope.


Expert Solution
Questions # 11:

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

Options:

A.

Assign an experienced resource to support the team member


B.

Escalate the team member's performance to the project sponsor


C.

Ask the team member to learn the new system as on-the-job training


D.

Issue a change request to extend the project schedule


Expert Solution
Questions # 12:

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

Options:

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.


B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.


C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.


D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.


Expert Solution
Questions # 13:

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves


B.

Discuss the issue with the steering committee to determine the proper course of action.


C.

Coordinate a video conference with the offending team member to resolve the issue


D.

Reassign the offending team member to a different project


Expert Solution
Questions # 14:

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.

Discuss the vacation plan and include scheduling changes in the change log database.


B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.


C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.


D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.


Expert Solution
Questions # 15:

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

Options:

A.

Start with the end user documentation review with the customer and gather feedback


B.

Start with design of the prototype review with the customer and gather feedback


C.

Start with the product prototype development, review with the customer, and gather feedback


D.

Start with the product architecture review with the customer and gather feedback


Expert Solution
Questions # 16:

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

Options:

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.


B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.


C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,


D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.


Expert Solution
Questions # 17:

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.


B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.


C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.


D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times


Expert Solution
Questions # 18:

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.

Support the team member by removing the blockers and impediments.


B.

Allocate the blockers and impediments to the product owner to resolve.


C.

Insist that the person who raised the blockers and impediments take ownership.


D.

Add any blockers or impediments to the risk register,


Expert Solution
Questions # 19:

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,


B.

Continue working with the predictive approach to deliver the value at the end of the project.


C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.


D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.


Expert Solution
Questions # 20:

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget


B.

Engaged with the project sponsor to ensure support for the project manager's decision


C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped


D.

Convinced the functional manager to stop the activities that will run beyond the budget


Expert Solution
Questions # 21:

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.

Discuss the issue with the team to resolve the disagreement.


B.

Ensure that there is consensus among the project stakeholders.


C.

Discuss the issue during the next sprint planning meeting.


D.

Support the outcome of the architects’ agreement.


Expert Solution
Questions # 22:

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.

Use a third-party instant messaging tool.


B.

Use a password-enabled audio/video product,


C.

Use a popular social media platform.


D.

Use a collaborative electronic whiteboard,


Expert Solution
Questions # 23:

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan


B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis


C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge


D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project


Expert Solution
Questions # 24:

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.

Document the issues and extend the project delivery timeline.


B.

Convene the steering committee and inform them of the impact to the project.


C.

Prioritize the user stories with issues and have the team resolve them


D.

Update the project management plan and risk management plan.


Expert Solution
Questions # 25:

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every

iteration.


B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.


C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.


D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential

information.


Expert Solution
Questions # 26:

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project


B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful


C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor


D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project


Expert Solution
Questions # 27:

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Options:

A.

Check the change management plan


B.

Document the issue in the scope management plan.


C.

Conduct a team brainstorming session to resolve the issue


D.

Check the quality management plan


Expert Solution
Questions # 28:

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue


B.

Validate the reason and add n as an issue m the issue log


C.

Escalate the issue to the functional manager


D.

Direct the sales team to speak with accounting to resolve the issue


Expert Solution
Questions # 29:

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.


B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.


C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.


D.

Check with human resources (HR) regarding the availability of staff.


Expert Solution
Questions # 30:

An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.

What should the project manager do next?

Options:

A.

Discuss the issue with the management team.


B.

Engage the project stakeholders.


C.

Update the contract with a lower rate,


D.

Engage the procurement team.


Expert Solution
Questions # 31:

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.

Reject the risk because the team is not in agreement on escalating it


B.

Include the risk in the risk assessment and evaluate it with the team


C.

Accept the risk and immediately enter the risk into the risk register


D.

Discuss with the consultant to understand why the risk was escalated


Expert Solution
Questions # 32:

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

Options:

A.

Accept the change request from country A and reschedule the deployment project for country A.


B.

Take the request into account and ask the sponsor to inform countries B and C about the change


C.

Ask country A to submit a change request that will be analyzed along with countries B and C


D.

Refuse country As request as there is no time for the change as deployment has already begun


Expert Solution
Questions # 33:

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.


B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.


C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).


D.

Ask the client to initiate a change request to make the director accountable for the

decision.


Expert Solution
Questions # 34:

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.


B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.


C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.


D.

Perform a gap analysis on renting in each of the locations.


Expert Solution
Questions # 35:

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.


B.

Conduct project reviews.


C.

Perform retrospectives.


D.

Complete sprint reviews


Expert Solution
Questions # 36:

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

Options:

A.

Ask the team member to learn the new system as on-the-job training


B.

Issue a change request to extend the project schedule


C.

Escalate the team members performance to the project sponsor


D.

Assign an experienced resource to support the team member


Expert Solution
Questions # 37:

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.


B.

Report the concern to the agile project management office (PMO),


C.

Inform the product owner of the concern so that i can be addressed.


D.

Open up to the team to work collaboratively to achieve the outcomes.


Expert Solution
Questions # 38:

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?

Options:

A.

Monitored progress in achieving the business value throughout the project


B.

Asked for additional time to achieve the project goals and increase business value


C.

Increased the number of project resources to ensure attainment of the business value


D.

Reviewed previous projects’ lessons learned and applied them to this project


Expert Solution
Questions # 39:

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.


B.

Inform the senior manager that they will need a new project management plan for this feature,


C.

Complete the most current feature and release the resources for the new feature.


D.

Analyze the impact of this change and present the options to the senior manager.


Expert Solution
Questions # 40:

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.

Propose using a compliance review board that will be responsible for approving all

product features prior to their release to the public.


B.

Liaison with the compliance group, making them responsible for understanding the

requirements and keeping them prioritized in the backlog.


C.

Meet with the compliance team and make sure that their requirements are covered in the

definition of done (DoD) for each story.


D.

Ensure that the peer review process also covers compliance requirements, creating a

second layer of security for the project.


Expert Solution
Questions # 41:

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

Options:

A.

Include the local union representative in the high-power, high-impact stakeholder group


B.

Focus on the sideward stakeholders only and let the organization manage the community.


C.

Build channels to extend communication efforts to the local community


D.

Use the city administration to address communication with the community


Expert Solution
Questions # 42:

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.


B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.


C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.


D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,


Expert Solution
Questions # 43:

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.

Escalate a schedule risk to the sponsor.


B.

Conduct team-building exercises.


C.

Stop the project and perform a team skill assessment.


D.

Make sure that the team has a full understanding of the scope.


Expert Solution
Questions # 44:

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.

Reviewed the project management plan


B.

Created a detailed operations manual


C.

Increased support hours for the hours of operation


D.

Involved operations stakeholders during planning


Expert Solution
Questions # 45:

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.


B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.


C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.


D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.


Expert Solution
Questions # 46:

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

Options:

A.

Ask the team to solve the issue internally and review the underperforming resource's situation


B.

Meet with the team member privately to discuss the problem and work together to find a solution


C.

Contact the functional manager and request to replace the team member with a better resource


D.

Discuss various options to improve the team member's performance with their functional managers


Expert Solution
Questions # 47:

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.


B.

Refer to the lessons learned to determine the impact on the external environment.


C.

Recommend postponing the project until the uncertainty is resolved,


D.

Highlight the concern to the project sponsor in the next project review meeting,


Expert Solution
Questions # 48:

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

Options:

A.

Ask senior management to communicate with these departments.


B.

Hire a project management consultant to help resolve the issue


C.

Convince senior management to introduce rewards to resisting departments.


D.

Understand the user concerns and revisit the stakeholder engagement plan


Expert Solution
Questions # 49:

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.

Planned all required training for the team during the onboarding process


B.

Identified all required skills after the kick-off of the project


C.

Identified all required skills during the planning of the project


D.

Asked the sponsor to identify all required skills during the planning of the project


Expert Solution
Questions # 50:

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.


B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,


C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,


D.

Begin discussions with other functional managers and meet with the accounting manager later.


Expert Solution
Viewing page 1 out of 12 pages
Viewing questions 1-50 out of questions