Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 5 out of 12 pages
Viewing questions 201-250 out of questions
Questions # 201:

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

Options:

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.


B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.


C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.


D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.


Expert Solution
Questions # 202:

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

Options:

A.

Ask the project team to delay the kick-off while resolving the concern.


B.

Request a copy of the project assumptions log for more insight.


C.

Meet with the project sponsor to obtain more information.


D.

Consult with the project team members to gain their opinions.


Expert Solution
Questions # 203:

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

Options:

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.


B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.


C.

A hybrid approach will allow the project manager to revise the product specifications.


D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.


Expert Solution
Questions # 204:

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.


B.

Evaluate and decide on a phased project management approach.


C.

Implement an adaptive project management approach.


D.

Use a hybrid model to combine predictive and adaptive life cycles.


Expert Solution
Questions # 205:

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

Options:

A.

Add the new requirements to the project scope immediately since they are mandatory changes.


B.

Review the new requirements with the compliance department to determine if a change request is needed.


C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.


D.

Proceed with the defined project requirements and delay implementing the new requirements.


Expert Solution
Questions # 206:

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

Options:

A.

After full development is completed


B.

When a major feature is completed


C.

At the end of each and every iteration


D.

When the sponsor approves the increment


Expert Solution
Questions # 207:

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

Options:

A.

Ask the members to be more proactive and share ideas with each other.


B.

Set up a daily virtual meeting with the development team.


C.

Plan a monthly virtual meeting to align and to review the plans.


D.

Review the issue with the project sponsor and ask for support.


Expert Solution
Questions # 208:

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

Options:

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.


B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.


C.

Add this item to the issue log and explore possible resolution options with the team.


D.

Update the risk register indicating that a new technology must be chosen by the team lead.


Expert Solution
Questions # 209:

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.

Design an updated status report.


B.

Request a meeting with the stakeholder.


C.

Escalate this to the project sponsor.


D.

Forward the project status reports.


Expert Solution
Questions # 210:

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.


B.

Implement a requirements traceability matrix.


C.

Add the requirements to the project charter.


D.

Understand the project management plan.


Expert Solution
Questions # 211:

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.


B.

Coach the project owner about the implications of unplanned meetings.


C.

Discuss the issue with the project owner at the retrospective meeting.


D.

Escalate the situation to management because it is affecting the team.


Expert Solution
Questions # 212:

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

Options:

A.

Monitor all stakeholders.


B.

Keep all stakeholders informed.


C.

Analyze the stakeholders.


D.

Engage the stakeholders.


Expert Solution
Questions # 213:

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.


B.

Share project updates through regular community meetings.


C.

Share the annual reports virtually and in the local newspapers.


D.

Share the project reports with the sponsor to inform community members.


Expert Solution
Questions # 214:

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

Options:

A.

Discuss the issue with the virtual team members and revise the communications management plan.


B.

Escalate this issue to the virtual team members' supervisors.


C.

Add this issue to the risk management plan and take action if it persists.


D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.


Expert Solution
Questions # 215:

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

Options:

A.

Submit a change order request with the new project objective to the project management office (PMO).


B.

Initiate a crashing routine to gain extra time for the added feature.


C.

Communicate the results and negotiate the needed resources and time with the stakeholder.


D.

Ask the project team to work overtime in order to accommodate the new changes.


Expert Solution
Questions # 216:

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

Options:

A.

Traditional delivery, to ensure high quality and that the product meets market demands


B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product


C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration


D.

Incremental delivery, to ensure that mobile capability is released fast to the users


Expert Solution
Questions # 217:

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.

Ask the project management office (PMO) to support and review all deliverables.


B.

Log the issue in the risk register and the issue log.


C.

Assign a technical writer to the project.


D.

Develop a standard for document quality control.


Expert Solution
Questions # 218:

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.


B.

Review similar projects in the company.


C.

Set the project's purpose, mission, and vision.


D.

Carry out the product backlog creation.


Expert Solution
Questions # 219:

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.


B.

Provide team members with specific and clear instructions on the project objectives and tasks.


C.

Communicate the project's impact and plans to engage the project team throughout the project.


D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.


Expert Solution
Questions # 220:

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

Options:

A.

Schedule a high-priority meeting with the project stakeholders to discuss the issue.


B.

Initiate a change request to obtain additional funds from the management reserve.


C.

Meet with the project team and customer to brainstorm about potential solutions.


D.

Collaborate with the relevant stakeholders on implementing the risk response plan.


Expert Solution
Questions # 221:

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

Options:

A.

Perform tests and routinely track results as per the quality management plan.


B.

Make sure the stakeholders are aware of the acceptance criteria.


C.

Negotiate to obtain approval if most of the tests have passed.


D.

Modify the acceptance criteria before the official delivery.


Expert Solution
Questions # 222:

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

Options:

A.

Keep the team engaged and focused on the project's direction.


B.

Encourage the team to do a brainstorming session and provide a mitigation plan.


C.

Focus on the resource management plan and track project progress,


D.

Set a clear vision for the project and ensure it is visible to all stakeholders.


E.

Organize a team-bonding activity and invite an external manager to speak to the team.


Expert Solution
Questions # 223:

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.


B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.


C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.


D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.


Expert Solution
Questions # 224:

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

Options:

A.

Request that the project team change their task deliverables to reflect the project sponsor's requirements.


B.

Set up a daily standup and request that the project sponsor attend to understand the project's tasks and deliverables.


C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.


D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.


Expert Solution
Questions # 225:

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control


B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.


C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.


D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.


Expert Solution
Questions # 226:

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

Options:

A.

Use the team's connections with international colleagues to get early warnings on future changes.


B.

Keep the focus on the priority items while the change goes through the change control process.


C.

Reject the change request since it may negatively impact the project's performance.


D.

Implement the change request as soon as possible to avoid accumulating new scope.


Expert Solution
Questions # 227:

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

Options:

A.

Plan a training session for the new team members not familiar with the system.


B.

Communicate the rules and criteria to the team members through email.


C.

Work only with the team members familiar with the system


D.

Document which rules and criteria the new team members are not familiar wit


Expert Solution
Questions # 228:

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.


B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.


C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.


D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.


Expert Solution
Questions # 229:

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.


B.

Encourage both team members to meet as soon as possible and resolve the problem


C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.


D.

Report the disruptive team member to the human resource (HR) department.


Expert Solution
Questions # 230:

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.

Allow the agile team to decide what they are able to deliver in each iteration


B.

Ask the team for additional feedback and add tasks to the task board,


C.

Hold a brainstorming session to identify the root cause of the complaints.


D.

Document the customer's complaints and critical issues in the issue log.


Expert Solution
Questions # 231:

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.


B.

Include project stakeholder expectations and needs while creating project acceptance criteria.


C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.


D.

Discuss project acceptance criteria with the project sponsor before the execution phase.


Expert Solution
Questions # 232:

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed


B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early


C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated


D.

In the initiation process, as it happens concurrently with the project contract and project charter creation


Expert Solution
Questions # 233:

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.


B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.


C.

The mentor will be immediately available to take over the project if there are problems or project delays.


D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.


E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.


Expert Solution
Questions # 234:

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Options:

A.

Require that all team members be physically present for the weekly project review.


B.

Offer the team member an incentive to stay until the end of the project.


C.

Replace the team member with someone who has similar qualifications and is located closer.


D.

Set up a weekly video conference to monitor the progress of the team member's work.


Expert Solution
Questions # 235:

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start


B.

Start to start


C.

Start to finish


Expert Solution
Questions # 236:

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

Options:

A.

Avoid conflict and let the team self-organize on how they want to work on the project tasks.


B.

Ask the project sponsor to provide team members with a project direction regarding outcomes.


C.

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.


D.

Escalate the situation to the steering committee and request that more time be allotted to the project.


Expert Solution
Questions # 237:

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

Options:

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.


B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.


C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.


D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.


Expert Solution
Questions # 238:

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.


B.

Ask the human resources (HR) manager for an external replacement.


C.

Log the situation in the issue log.


D.

Update the key stakeholders on the issue.


Expert Solution
Questions # 239:

A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even

though reports have been sent on a weekly basis.

What should the project manager do to ensure all stakeholders are receiving proper information about the project?

Options:

A.

Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.


B.

Create daily progress reports and send them to all stakeholders.


C.

Include stakeholders in the weekly status meetings with the team.


D.

Assess all of the project stakeholders and document their preferred communication method and frequency.


Expert Solution
Questions # 240:

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

Options:

A.

Escalate this to the project director for a resolution.


B.

Escalate this to the agile lead of the second team.


C.

Review the process and remove the impediment.


D.

Remove the certification need from the project scope.


Expert Solution
Questions # 241:

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

Options:

A.

The organizational process assets (OPAs) have been updated.


B.

The contractual deliverables of the project have been accepted.


C.

It The handover and deliverable acceptance have been completed.


D.

The lessons learned sessions have been conducted.


Expert Solution
Questions # 242:

A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

Options:

A.

Update the risk management plan.


B.

Extend the timeline of the project.


C.

Check the organizational process assets (OPAs).


D.

Acquire knowledgeable resources.


Expert Solution
Questions # 243:

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Question # 243


Expert Solution
Questions # 244:

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.


B.

Request a revision of the procurement contract to include specifications for the parts.


C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.


D.

Review the procurement contract and ask the supplier to negotiate a solution.


Expert Solution
Questions # 245:

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

Options:

A.

Use the existing budget for executing the fallback plan and update the baseline.


B.

Add additional resources to the project to fast track certain activities and reduce delays.


C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.


D.

Communicate the delay to stakeholders and maintain the existing budget baseline.


Expert Solution
Questions # 246:

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options:

A.

30/40


B.

40/70


C.

30/70


D.

40/30


Expert Solution
Questions # 247:

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.


B.

Propose an approach based on value measurement, such as the use of objectives and key results.


C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.


D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.


Expert Solution
Questions # 248:

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.


B.

Use a kanban board to increase accountability.


C.

Use a product backlog to manage changes.


D.

Use a burnup chart to provide transparency.


Expert Solution
Questions # 249:

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

Options:

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.


B.

Escalate the issue to the functional manager and ask for support.


C.

Involve all stakeholders in the project by distributing status reports.


D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.


E.

Engage all stakeholders in the project including the unsupportive stakeholders.


Expert Solution
Questions # 250:

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.


B.

Confirm with the team members that the functional manager is responsible for the delivery.


C.

Ask the product owner to clarify the roles and responsibilities of the project team.


D.

Inform the functional manager that task allocation is the responsibility of the product owner.


Expert Solution
Viewing page 5 out of 12 pages
Viewing questions 201-250 out of questions