A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.
How should the project manager resolve this conflict?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The
procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.
How should the project manager approach this project?
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a
predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams
are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current
impediments.
What should the project manager do?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to
ensure the community members are up to date on project progress?
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
What immediate corrective action should the project manager take?
At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting
with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next ?
A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.
What should the project manager do?
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?
While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project
manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a
dependency missing between:
+ Test the product
+ Release to customer
According to the quality management plan, the product must be tested before being released.
How should the project manager enter this dependency?
A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team
members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?
A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even
though reports have been sent on a weekly basis.
What should the project manager do to ensure all stakeholders are receiving proper information about the project?
An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?
A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.
What should the project manager do?
In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.
What should the project manager propose?
A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)
needs visibility of the regulatory constraints while maintaining a degree of flexibility.
Which tool can the project manager use?
A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that
some stakeholders are working against the success targets of the project.
What should the project manager do to ensure successful project delivery? (Choose two)
During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?