PMI Project Management Professional (2025 Version) PMP Question # 247 Topic 25 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 247 Topic 25 Discussion

PMP Exam Topic 25 Question 247 Discussion:
Question #: 247
Topic #: 25

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?


A.

Schedule a meeting between the team members to find a solution.


B.

Refer the team members to the project charter to resolve the conflict.


C.

Issue a new change request to evaluate this situation and communicate the result.


D.

Document the facts explained by the team members in the issue log.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.