Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 245 Topic 25 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 245 Topic 25 Discussion

PMP Exam Topic 25 Question 245 Discussion:
Question #: 245
Topic #: 25

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?


A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.


B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.


C.

Delegate authority to the team members and ask them to submit weekly status reports instead.


D.

Ask senior management for permission to hold in-person team meetings once each week.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.