PMI Project Management Professional (2025 Version) PMP Question # 240 Topic 25 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 240 Topic 25 Discussion

PMP Exam Topic 25 Question 240 Discussion:
Question #: 240
Topic #: 25

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?


A.

Help the team create the definition of done (DoD) to improve delivery quality.


B.

Add testing items to the backlog to assess quality periodically.


C.

Expand the team in order to improve the quality of the project.


D.

Compare the cost of improving quality against the cost of failure and adjust the budget.