Question #: 240
Topic #: 25

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?


A.

Evaluate the impact to the users and create a plan to address it.


B.

Inform users about the new changes and ask for their collaboration.


C.

Ask all managers to collaborate implementing this change to users.


D.

Start implementing the change so that users will eventually get used to it.