A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
A.
Place the new team member on a performance improvement program.
B.
Ask another team member to take some of the new team member's work.
C.
Assign easier activities to the new team member.
D.
Allocate time within the iterations to mentor the new team member.
Integrating a new team member into an iterative project requires a supportive approach that ensures they understand the processes and can contribute effectively. Allocating time within the iterations for mentoring allows the new member to learn the necessary skills and processes in a structured manner. This aligns with the PMBOK® Guide’s principles of project team management and development, which emphasize the importance of continuous learning and improvement within the team. Mentoring provides a practical way to facilitate this learning, helping the new member to integrate into the team’s workflow without negatively impacting the schedule1.
Mentoring - Key Competency for Program and Project Professionals - PMI1.