PMI Project Management Professional (2025 Version) PMP Question # 250 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 250 Topic 26 Discussion

PMP Exam Topic 26 Question 250 Discussion:
Question #: 250
Topic #: 26

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?


A.

Ask for additional team members to maintain the velocity


B.

Implement a checkpoint in the iteration to verify if the team is on track


C.

Conduct a focused retrospective to help the team to discover the root cause


D.

Ask the team to have a lower commitment for the next iteration


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.