Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 250 Topic 26 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 250 Topic 26 Discussion

PMP Exam Topic 26 Question 250 Discussion:
Question #: 250
Topic #: 26

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?


A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.


B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.


C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.


D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.