Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 250 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 250 Topic 26 Discussion

PMP Exam Topic 26 Question 250 Discussion:
Question #: 250
Topic #: 26

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall

progress.

What should the project manager do next?


A.

Capture this in the issue log and escalate it to the project sponsor.


B.

Meet with the stakeholder to understand what is causing the delays.


C.

Facilitate a brainstorming session to find potential workarounds.


D.

Discuss the need to influence this stakeholder with the sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.