PMI Project Management Professional (2025 Version) PMP Question # 249 Topic 25 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 249 Topic 25 Discussion

PMP Exam Topic 25 Question 249 Discussion:
Question #: 249
Topic #: 25

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?


A.

Use the existing budget for executing the fallback plan and update the baseline.


B.

Add additional resources to the project to fast track certain activities and reduce delays.


C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.


D.

Communicate the delay to stakeholders and maintain the existing budget baseline.