PMP Exam Topic 24 Question 239 Discussion:
Question #: 239
Topic #: 24

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?


A.

Request additional budget to recruit more developers.


B.

Lower the recruitment criteria.


C.

Log the issue in the issue log.


D.

Analyze the impact and inform the stakeholders.