Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 238 Topic 24 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 238 Topic 24 Discussion

PMP Exam Topic 24 Question 238 Discussion:
Question #: 238
Topic #: 24

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?


A.

Ask the project management office (PMO) to support and review all deliverables.


B.

Log the issue in the risk register and the issue log.


C.

Assign a technical writer to the project.


D.

Develop a standard for document quality control.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.