PMI Project Management Professional (2025 Version) PMP Question # 238 Topic 24 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 238 Topic 24 Discussion

PMP Exam Topic 24 Question 238 Discussion:
Question #: 238
Topic #: 24

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?


A.

Reschedule the project execution date.


B.

Continue project execution using the current blueprints from the client.


C.

Escalate this issue to the project sponsor


D.

Consult with the client to determine if project execution should be continued.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.