Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 208 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 208 Topic 21 Discussion

PMP Exam Topic 21 Question 208 Discussion:
Question #: 208
Topic #: 21

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?


A.

Ensure the activities of this team member are distributed across the project team.


B.

Assess a mechanism for knowledge transfer among the team members.


C.

Motivate the team member to stay by providing them with incentives.


D.

Ask human resources (HR) to counsel the team member to balance the workload.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.