PMI Project Management Professional (2025 Version) PMP Question # 208 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 208 Topic 21 Discussion

PMP Exam Topic 21 Question 208 Discussion:
Question #: 208
Topic #: 21

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?


A.

Provided copies of the stakeholder engagement plan to all team members.


B.

Defined the roles and responsibilities of the team members.


C.

Updated the communications management plan.


D.

Established ground rules for the team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.