PMI Project Management Professional (2025 Version) PMP Question # 206 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 206 Topic 21 Discussion

PMP Exam Topic 21 Question 206 Discussion:
Question #: 206
Topic #: 21

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?


A.

Guide the team member on how to resolve the conflict.


B.

Analyze the project schedule and look for alternatives.


C.

Perform crashing and/or fast tracking of the schedule.


D.

Meet the team member and try to plan a course of action together.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.