Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 206 Topic 21 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 206 Topic 21 Discussion

PMP Exam Topic 21 Question 206 Discussion:
Question #: 206
Topic #: 21

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?


A.

Apply appropriate conflict resolution techniques to solve the issue.


B.

Call a team meeting to have a formal discussion of the issue.


C.

Allow the team to work through it on their own unless help is needed.


D.

Engage in individual conversation with each team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.