Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 206 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 206 Topic 21 Discussion

PMP Exam Topic 21 Question 206 Discussion:
Question #: 206
Topic #: 21

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?


A.

Sprint plan and product roadmap


B.

Product roadmap and sprint backlog


C.

Product backlog and scrum board


D.

Sprint backlog and scrum board


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.