PMI Project Management Professional (2025 Version) PMP Question # 203 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 203 Topic 21 Discussion

PMP Exam Topic 21 Question 203 Discussion:
Question #: 203
Topic #: 21

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?


A.

Add the issue to the issue log and determine the corrective action.


B.

Create a fishbone diagram to determine the root cause for the misunderstanding.


C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.


D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.