Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 202 Topic 21 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 202 Topic 21 Discussion

PMP Exam Topic 21 Question 202 Discussion:
Question #: 202
Topic #: 21

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?


A.

Reach an agreement with the team on how to handle the situation.


B.

Reach out to the procurement team to hire a substitute for the team member.


C.

Allow senior management to decide how to proceed with the project.


D.

Convince the team member not to leave until the project is completed.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.