PMI Project Management Professional (2025 Version) PMP Question # 202 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 202 Topic 21 Discussion

PMP Exam Topic 21 Question 202 Discussion:
Question #: 202
Topic #: 21

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?


A.

Escalate the issue to the team's manager.


B.

Remove some of the team members.


C.

Review the roles and responsibilities document.


D.

Develop working agreements with the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.