PMI Project Management Professional (2025 Version) PMP Question # 98 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 98 Topic 10 Discussion

PMP Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?


A.

Reviewed the communications management plan before inviting an external client representative to the meeting


B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting


C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register


D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.