PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?


A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.


B.

Work with the team to understand what can motivate them to try and complete the project.


C.

Remind the team of their commitment with the client and the need to adapt to the client's needs.


D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.