PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)


A.

Require a written status report from all team members on a weekly basis


B.

Form a core group of team leads representing members from each country and encourage them to collaborate


C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day


D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.