Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 65 Topic 7 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 65 Topic 7 Discussion

PMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?


A.

Perform a qualitative risk analysis and update the risk register.


B.

Submit a change request through the Integrated change control process.


C.

Update the issue log and discuss It in the next steering committee meeting.


D.

Estimate the associated costs and increase the project budget accordingly.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.