New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 65 Topic 7 Discussion

PMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?


A.

Discuss the definition of done (DoD) with the customer.


B.

Approach the product owner to determine the next course of action and update the backlog.


C.

Discuss the acceptance criteria with customer.


D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.