PMI Project Management Professional (2025 Version) PMP Question # 70 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 70 Topic 8 Discussion

PMP Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?


A.

Ask the project team to meet and document why the stakeholder's approach is incorrect.


B.

Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.


C.

Discuss the issue with the project team during a project status meeting and request that they change the approach.


D.

Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.