Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 70 Topic 8 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 70 Topic 8 Discussion

PMP Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?


A.

Budget estimate


B.

Definitive estimate


C.

Story points


D.

Order of magnitude


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.