A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?


A.

11 days


B.

12.5 days


C.

12 days


D.

11.5 days