New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 166 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 166 Topic 17 Discussion

PMP Exam Topic 17 Question 166 Discussion:
Question #: 166
Topic #: 17

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is

a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service

team is overwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose two)


A.

Contact the customers in batches and inform them that the issues are being worked on currently.


B.

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.


C.

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.


D.

Ask senior management to replace the customer service manager with a more qualified one.


E.

Request that the customer service team prioritizes work on queries that are received this week.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.