PMI Project Management Professional (2025 Version) PMP Question # 166 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 166 Topic 17 Discussion

PMP Exam Topic 17 Question 166 Discussion:
Question #: 166
Topic #: 17

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?


A.

Revisit the communications management plan and make necessary adjustments


B.

Revisit the scope management plan and note this as a risk


C.

Schedule a meeting with the product owner and finance team to agree on course corrections


D.

Continue developing based on the project management plan and address the issue post delivery


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.