PMI Project Management Professional (2025 Version) PMP Question # 165 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 165 Topic 17 Discussion

PMP Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?


A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project


B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,


C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable


D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.