Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 165 Topic 17 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 165 Topic 17 Discussion

PMP Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?


A.

Discuss the issue with the team to resolve the disagreement.


B.

Ensure that there is consensus among the project stakeholders.


C.

Discuss the issue during the next sprint planning meeting.


D.

Support the outcome of the architects’ agreement.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.