PMI Project Management Professional (2025 Version) PMP Question # 165 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 165 Topic 17 Discussion

PMP Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?


A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.


B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.


C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.


D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.