New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMP Exam Topic 17 Question 167 Discussion:
Question #: 167
Topic #: 17

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?


A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.


B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reactiontime.


C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.


D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.