PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMP Exam Topic 17 Question 167 Discussion:
Question #: 167
Topic #: 17

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?


A.

Request a replacement resource


B.

Perform a cost-benefit analysis


C.

Implement risk responses


D.

Perform Integrated Change Control


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.