PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 167 Topic 17 Discussion

PMP Exam Topic 17 Question 167 Discussion:
Question #: 167
Topic #: 17

During a risk review meeting early in a project, the project team flags the possibility that a key team member might be away during the implementation of a key work package. Unfortunately, this team member is currently the only resource with the knowledge to perform this work, although it is possible someone else could do it with training.

What should the project manager do?


A.

Establish a long-term training program for the junior team members.


B.

Reassign the tasks among team members to allow them to split the workload.


C.

Ask team members to document knowledge assets for all the tasks.


D.

Ensure team members collaborate throughout the project to share knowledge.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.