PMI Project Management Professional (2025 Version) PMP Question # 113 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 113 Topic 12 Discussion

PMP Exam Topic 12 Question 113 Discussion:
Question #: 113
Topic #: 12

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?


A.

Escalate the matter to the executive board so they can decide on next steps


B.

Prioritize the project backlog and ask the development team to fix the issues


C.

Review the project's benefits management plan with the product owner.


D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.