PMI Project Management Professional (2025 Version) PMP Question # 113 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 113 Topic 12 Discussion

PMP Exam Topic 12 Question 113 Discussion:
Question #: 113
Topic #: 12

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?


A.

Ask the vice president to approve the project charter to kick off the project


B.

Ask the vice president to define who will be the product owner for the project


C.

Investigate if the value and benefits of the project are identified


D.

Start working on the project immediately and determine the scope later


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.