PMI Project Management Professional (PMBOK 7th Version) PMP Question # 615 Topic 62 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 615 Topic 62 Discussion

PMP Exam Topic 62 Question 615 Discussion:
Question #: 615
Topic #: 62

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?


A.

Allow project B's leader to continue building relationships.


B.

Talk with project B's leader to discuss possible impacts to both projects.


C.

Tell project A's team member to ignore project B's leader.


D.

Ensure project A's team member can finish the work committed to project A.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.