PMP Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A project manager has recently conducted a kickoff meeting for a project aimed at updating a product for a client in the insurance services sector. The product owner

has given notice of their departure from the company in two months, prompting the client to express concerns about the change in personnel.

What should the project manager do?


A.

Ask the project sponsor ' s opinion about continuing the project.


B.

Meet with the team to discuss the product owner ' s replacement.


C.

Add the risk and mitigations to the risk register.


D.

Meet with the client to understand and address their concerns.