Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 16 Topic 2 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 16 Topic 2 Discussion

PMP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

A project creating a new search engine has been ongeing for several years. Some original features are no longer relevant and will be replaced, due to advancements

with artificial intelligence (Al). A team member has raised concern that one backlog item falls in that category.

What should the project manager do?


A.

Use several Al tools to find an appropriate solution and implement it.


B.

Suggest the project team align and agree on Al items that are still relevant.


C.

Raise the concern with the product owner to determine if the item is still relevant.


D.

Ask the project sponsor to decide if the concern is valid and if it should be removed.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.