New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 16 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 16 Topic 2 Discussion

PMP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?


A.

Update the stakeholder engagement plan to include the CEO.


B.

Meet with the CEO to review the current deliverables for the project.


C.

Identify the CEO's preferred method of communication.


D.

Send the updated project management plan and documents to the CEO.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.