PMI Project Management Professional (2025 Version) PMP Question # 16 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 16 Topic 2 Discussion

PMP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?


A.

Request a decision from the project sponsor.


B.

Give approval of the technical specifications.


C.

Ask the sponsor for additional funding to hire a senior subject matter expert (SME).


D.

Schedule a meeting with all of the subject matter experts (SMEs) to discuss.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.