Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 3 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 3 Topic 1 Discussion

PMP Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?


A.

Recommend a change in the project methodology or the approach.


B.

Develop and execute a stakeholder engagement strategy.


C.

Determine the criteria and measuring systems for objective success.


D.

Allocate more time for mentoring project team members.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.