Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 3 Topic 1 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 3 Topic 1 Discussion

PMP Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A project manager has been assigned to complete a project within the approved budget. Midway through the implementation, the project budget is reduced by the

sponsor.

What should the project manager do?


A.

Lower costs to align with the new budget and update the team.


B.

Replace the project team with new staff to comply with the new budget.


C.

Consult the stakeholders to update the project management plan with the new budget.


D.

Pause the project and update the project management plan with the new budget.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.