PMI Project Management Professional (2025 Version) PMP Question # 3 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 3 Topic 1 Discussion

PMP Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?


A.

Facilitate a supportive level of engagement for this stakeholder.


B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.


C.

Perform a qualitative risk analysis using a probability and impact matrix.


D.

Ensure the key information is accurate and monitor the situation as the project progresses.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.