PMP Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

During a project kickoff meeting, two key stakeholders are arguing about the project scope and the acceptance of the deliverable. What should the project manager focus on to address the argument?


A.

Escalate the stakeholder misalignment with the project sponsor and seek direction for the deliverables.


B.

Update the risk register first with scope discrepancies and then escalate it to the next level.


C.

Arrange brainstorming with the stakeholders to complete the project scope statement and finalize the deliverable.


D.

Reference the business case and confirm the common understanding of the project objectives and value creation.