New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 40 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 40 Topic 5 Discussion

PMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.

What should the project manager do?


A.

Review and update the project management plan to accommodate the delays.


B.

Speak with the project sponsors about changing the project management plan.


C.

Create a change request to increase the cost of resources.


D.

Delay the project until additional resources can be identified.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.