Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 40 Topic 5 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 40 Topic 5 Discussion

PMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?


A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.


B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.


C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.


D.

Meet with the team member and search for the root cause of their behavior.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.