PMI Project Management Professional (2025 Version) PMP Question # 40 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 40 Topic 5 Discussion

PMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?


A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.


B.

Reject the review as the completed project timeline is set by the company's CEO and has already been approved.


C.

Agree to review the architect's new proposal to assess the impact on the timelines set by the CEO.


D.

Register an issue in the log regarding the timeline delay to the CEO's approved plans before agreeing to change the project scope.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.