Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 40 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 40 Topic 5 Discussion

PMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split

across teams working independently in different regions; however, there are task dependencies between the two teams.

What should the team lead do?


A.

Ensure all team members participate in the meetings regardless of time zone challenges.


B.

Ensure each team creates and accesses relevant project artifacts to manage dependent tasks.


C.

Check if additional meetings are required with a time suitable for both teams.


D.

Assign the dependent tasks to team members in the same time zone to avoid issues.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.