Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 2 Topic 1 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 2 Topic 1 Discussion

PMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A project is approaching the closure phase. The project manager realizes that the team has consumed more hours than what was budgeted because some nonfunctional security requirements were not considered during project initiation.

What should the project manager do to avoid this issue in the future?


A.

Conduct a mandatory security awareness program for all project team members.


B.

Hold a retrospective on why the requirements were overlooked and update organizational process assets.


C.

Change the status in the risk register to issue and activate the response plan.


D.

Meet with team members of the security department and require the department to be involved from the project’s start.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.