Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 2 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 2 Topic 1 Discussion

PMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?


A.

Performing


B.

Storming


C.

Norming


D.

Forming


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.