PMI Project Management Professional (2025 Version) PMP Question # 2 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 2 Topic 1 Discussion

PMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?


A.

Appoint a dedicated product manager for the duration of the release


B.

Have the customer approve the product increment features.


C.

Ensure every user story has acceptance criteria.


D.

Track business outcomes for planned user stories.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.