PMP Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.

What should the team lead do next?


A.

Create all of the stories just for the next sprint and skip the epics until the next sprint.


B.

Create the epics at a high level for the requirements and begin grooming sessions.


C.

Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.


D.

Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.