Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 6 Topic 1 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 6 Topic 1 Discussion

PMP Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

Acustomer is complaining to the project manager that it takes too long for the change control board (CCB) to approve changes. The CCB has their own key

performance indicators (KPI) to manage the change lifecycle. Currently, they take 2 to 3 weeks to review and approve a change request, affecting the project

timelines and delivery.

What should the project manager do?


A.

Escalate the issue of change approval delays to the project management office (PMO) to address.


B.

Make changes to project governance to push decision-making authority down to team leads.


C.

Conduct root cause analysis to determine why the change process has recently changed.


D.

Brainstorm ways to reduce the cycle time and to speed up the change approval process.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.