Acustomer is complaining to the project manager that it takes too long for the change control board (CCB) to approve changes. The CCB has their own key
performance indicators (KPI) to manage the change lifecycle. Currently, they take 2 to 3 weeks to review and approve a change request, affecting the project
timelines and delivery.
What should the project manager do?