PMI Project Management Professional (2025 Version) PMP Question # 6 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 6 Topic 1 Discussion

PMP Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?


A.

Resource breakdown structure


B.

Work breakdown structure (WBS)


C.

Team charter


D.

Project charter


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.