PMI Project Management Professional (2025 Version) PMP Question # 47 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 47 Topic 5 Discussion

PMP Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?


A.

Validate assumptions using appropriate tools to assess the risks.


B.

Refer to the lessons learned to determine the impact on the external environment.


C.

Recommend postponing the project until the uncertainty is resolved,


D.

Highlight the concern to the project sponsor in the next project review meeting,


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.