New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 47 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 47 Topic 5 Discussion

PMP Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?


A.

Ask the team to adapt based on their current resources.


B.

Plan a meeting with the stakeholders to get more resources.


C.

Replan the upcoming deliverables based on the available tools.


D.

Ask the project sponsor to provide the needed resources.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.