Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 47 Topic 5 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 47 Topic 5 Discussion

PMP Exam Topic 5 Question 47 Discussion:
Question #: 47
Topic #: 5

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?


A.

Explain to the management team that reporting and management dashboards are not effective agile practices


B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant


C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)


D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.