New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 48 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 48 Topic 5 Discussion

PMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?


A.

Determine the average of the two estimates and assign that amount.


B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.


C.

Consult the lessons learned for insight into the correct estimate.


D.

Select the junior member's estimate since they will most likely be doing the work.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.