Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 48 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 48 Topic 5 Discussion

PMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A project manager is leading a hybrid manufacturing project. The company is in crisis mode, and the project sponsor has high expectations for the project team,

expecting them to deliver the project outcome even if they must struggle to do it. However, the project team is demotivated about the company ' s situation and are not

performing as expected.

What should the project manager do?


A.

Inform the project sponsor immediately that their expectations are impossible to fulfill and propose to close the project.


B.

Brainstorm with the project team about what can be successfully delivered, then negotiate to fit the sponsor ' s needs.


C.

Assure the sponsor that the team will deliver the expected results; wait to inform the project team of this assurance later.


D.

Contact the stakeholders for initial feedback regarding what to do about the sponsor ' s expectations.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.