PMI Project Management Professional (2025 Version) PMP Question # 48 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 48 Topic 5 Discussion

PMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?


A.

Ask senior management to communicate with these departments.


B.

Hire a project management consultant to help resolve the issue


C.

Convince senior management to introduce rewards to resisting departments.


D.

Understand the user concerns and revisit the stakeholder engagement plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.