A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.

What should the project manager do first?


A.

Increase the capacity of the team to finish the project on time.


B.

Update the risk register and present a contingency plan to meet the deadline.


C.

Ask the team to propose a minimum viable product (MVP) to meet the date.


D.

Suggest to the customer to reduce the backlog to meet the date.