Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 48 Topic 5 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 48 Topic 5 Discussion

PMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?


A.

Document the risk register in the project charter.


B.

Speak to the customer and add the issue to the issue log.


C.

Review user roles and update the team charter.


D.

Involve the product owner to rewrite the user stories.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.