PMI Project Management Professional (2025 Version) PMP Question # 14 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 14 Topic 2 Discussion

PMP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?


A.

Discuss with the team how the project objectives can be met.


B.

Request that the sponsor increase the bonus for high performers.


C.

Schedule a team-building activity to boost the team's morale.


D.

Organize a team meeting to remind the team of the ground rules.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.