Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 14 Topic 2 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 14 Topic 2 Discussion

PMP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?


A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.


B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country


C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.


D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.