PMI Project Management Professional (2025 Version) PMP Question # 14 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 14 Topic 2 Discussion

PMP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?


A.

Discuss the vacation plan and include scheduling changes in the change log database.


B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.


C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.


D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.