Question #: 22
Topic #: 3

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?


A.

Invite technical stakeholders for backlog prioritization.


B.

Work on the features already prioritized by the product owner.


C.

Ask the sponsor for more resources to continue at the same pace.


D.

Add the technical debt tasks to the sprint backlog.