PMI Project Management Professional (2025 Version) PMP Question # 23 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 23 Topic 3 Discussion

PMP Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?


A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan


B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis


C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge


D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.