PMP Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?


A.

Give the team members a few days off to reduce stress.


B.

Reduce the number of internal and external meetings.


C.

Review team assignments and reduce the workload.


D.

Schedule one-to-one meetings and team-building meetings.