PMI Project Management Professional (2025 Version) PMP Question # 21 Topic 3 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 21 Topic 3 Discussion

PMP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

A project manager prepared a project benefits management plan. Which of the following should be included in this document?


A.

Project requirements, target benefits, issue log, metrics


B.

Target benefits, strategic alignment, time frame for realizing benefits


C.

Strategic alignment, benefits owner, risk register


D.

Target benefits, benefits owner, lessons learned


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.