Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 19 Topic 2 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 19 Topic 2 Discussion

PMP Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

A project team repeatedly misses delivery target dates for the main project releases because of new requests from the client. Client satisfaction is high, even though the project is behind schedule.

What should the project manager do?


A.

Assess the impact of the new requests and advise the team of approval.


B.

Train the team on how to handle the risk of missing deadline targets.


C.

Assign the new requirements to the senior members to avoid delays.


D.

Allow additional time for the team to work on the new requests.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.