PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMP Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?


A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,


B.

Continue working with the predictive approach to deliver the value at the end of the project.


C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.


D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.