PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMP Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team's development stage. The project manager believes that the team has passed the "storming" stage.

Which indicators should be used to determine the team's development stage?


A.

Scrum ceremonies are held per the Scrum guide.


B.

Team members share information and experiences.


C.

Formal training courses have been completed by team members.


D.

Project deliverables are formally approved.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.