New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 19 Topic 2 Discussion

PMP Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.

Which are three fundamental actions the project manager should take? (Choose 3)


A.

Decide on the frequency of communications.


B.

Define key performance indicators (KPIs) to measure and report.


C.

Determine the appropriate methods of communication.


D.

Identify the level of detail needed by different stakeholders.


E.

Obtain executive approval on the communications management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.