PMI Project Management Professional (2025 Version) PMP Question # 17 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 17 Topic 2 Discussion

PMP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.

What should the project manager take into account first when building the schedule for this new project?


A.

The benchmarked velocities of the previously completed projects


B.

The benchmarked baselines of the previously completed projects


C.

The compliance needs and categories of the new project


D.

The compliance measurement criteria of the new project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.