Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 17 Topic 2 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 17 Topic 2 Discussion

PMP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?


A.

Notify all team members that all steps in the process must be completed.


B.

Escalate the issue to the other executive leadership members.


C.

Schedule a review of the process steps with the team and the COO.


D.

Redesign the process so the team can move more quickly.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.