PMI Project Management Professional (2025 Version) PMP Question # 17 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 17 Topic 2 Discussion

PMP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?


A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.


B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.


C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.


D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.