New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 12 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 12 Topic 2 Discussion

PMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?


A.

Give some advice to the team member to reduce their stress and anxiety.


B.

Review team participation in the next retrospective meeting with all team members.


C.

Reach out to the team member to discuss and address their concerns as soon as possible.


D.

Evaluate upcoming project deadlines and reorganize team member assignments.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.