PMI Project Management Professional (2025 Version) PMP Question # 12 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 12 Topic 2 Discussion

PMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?


A.

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.


B.

The scrum master should ensure the appropriate escalation to resolve the issues.


C.

The product owner owns the open issues until they are resolved.


D.

Individual team members need to submit service desk tickets to resolve the issues.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.