Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 12 Topic 2 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 12 Topic 2 Discussion

PMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?


A.

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.


B.

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.


C.

Request that the key resource's functional manager work directly with the resourceduring the project.


D.

Discuss this with the project sponsor and request that this key resource be replaced onthe project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.