Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 12 Topic 2 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 12 Topic 2 Discussion

PMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A project is delayed because of an unknown risk impacting the budget. The project manager requests the project management office review the recommendation for a

budget increase.

What should the project manager have done to avoid going over budget?


A.

Allocated a management reserve budget during planning.


B.

Asked the project sponsor to provide additional budget for the project.


C.

Reviewed the risk with the sponsor and advised on funding sources.


D.

Reviewed the risk management plan and activated the contingency actions.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.