Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 163 Topic 17 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 163 Topic 17 Discussion

PMP Exam Topic 17 Question 163 Discussion:
Question #: 163
Topic #: 17

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?


A.

Update the project management plan to reduce the possibility of scope creep.


B.

Schedule a regular risk review with the project management team.


C.

Increase the active engagement and participation of key stakeholders.


D.

Create a project change roadmap to keep track of all unforeseen changes.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.