PMI Project Management Professional (2025 Version) PMP Question # 163 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 163 Topic 17 Discussion

PMP Exam Topic 17 Question 163 Discussion:
Question #: 163
Topic #: 17

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?


A.

By scheduling iterative meetings with the product owner to improve project tracking


B.

By focusing on the delivery of incremental working products lo the customer


C.

By reviewing burnup charts to determine the effort required against estimated earned value


D.

By conducting daily standups to more accurately track project deliverables


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.