New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 163 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 163 Topic 17 Discussion

PMP Exam Topic 17 Question 163 Discussion:
Question #: 163
Topic #: 17

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project

and the customer.

What should the project manager do?


A.

Ask the team member to submit a formal change request.


B.

Accept the suggestion as it has no impact on the project.


C.

Ask another team member to validate the impacts of the suggestion.


D.

Reject the suggestion and ask the team member to focus on executing the plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.