PMI Project Management Professional (2025 Version) PMP Question # 158 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 158 Topic 16 Discussion

PMP Exam Topic 16 Question 158 Discussion:
Question #: 158
Topic #: 16

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?


A.

Determine potential threats regarding compliance with the regulations.


B.

Ask human resources (HR) to assign a compliance specialist to the team.


C.

Validate that the software is compliant with standards and regulations.


D.

Measure the extent to which the project complies with the regulations.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.