New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 158 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 158 Topic 16 Discussion

PMP Exam Topic 16 Question 158 Discussion:
Question #: 158
Topic #: 16

A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members

available who are qualified to complete the work.

What should the project manager do?


A.

Assess the team member's development requirements and arrange for the team member to receive training.


B.

Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.


C.

Work with the functional manager to determine an incentive for the team member to complete the project.


D.

Request a substitute for the team member with a new resource who is more skilled in system development work.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.