Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 158 Topic 16 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 158 Topic 16 Discussion

PMP Exam Topic 16 Question 158 Discussion:
Question #: 158
Topic #: 16

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?


A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.


B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.


C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,


D.

Determine what methods the team has been trained on and utilize those methods for the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.