New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMP Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?


A.

Understand the customer's perspective and provide mentoring on agile mindsets.


B.

Call for an internal team retrospective and create an improvement action plan.


C.

Ask the customer to work with the product owner to prioritize all requests.


D.

Work with the team to receive customer directions and improve the process.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.