PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMP Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)


A.

Rolling wave planning and an adaptive approach


B.

Relative estimation to determine the task or deliverable sizes


C.

Iterations and reviews to continuously keep adapting the plan


D.

Bottom-up estimating based on a work breakdown structure (WBS)


E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.