PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 68 Topic 7 Discussion

PMP Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

A project manager is reviewing the team's Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.

Will the project manager meet this objective?


A.

Yes, it will take 4 working days to complete these tasks based on the estimate.


B.

No, it will take 6 days to complete all these tasks based on the estimate.


C.

No, it will take 7 days to complete all these tasks based on the estimate.


D.

Yes, it will take 5 working days to complete these tasks based on the estimate.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.