PMI Project Management Professional (2025 Version) PMP Question # 155 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 155 Topic 16 Discussion

PMP Exam Topic 16 Question 155 Discussion:
Question #: 155
Topic #: 16

Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.

What should the scrum master do first in this situation?


A.

Divide the user stories into two categories: development stories and test stories.


B.

Increase the number of developers on the team so stories are completed faster.


C.

Revalidate the team's velocity to ensure development and testing can be completed within the iteration.


D.

Request the developers work overtime to ensure the testers have enough time to perform their tests.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.