PMI Project Management Professional (2025 Version) PMP Question # 155 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 155 Topic 16 Discussion

PMP Exam Topic 16 Question 155 Discussion:
Question #: 155
Topic #: 16

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)


A.

Risk steering committee


B.

Functional managers


C.

Board of directors


D.

Advisory team panel


E.

Chief executive officer


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.