A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?
A.
Use a work breakdown structure (WBS) with firm start and end dates for all phases to ensure nothing is missed.
B.
Use a kanban board as an information radiator to manage work in progress (WIP) at the individual and organizational levels.
C.
Use a minimum viable product (MVP) to test and discover which features to schedule when and what to fail early.
D.
Use a product backlog of the functionalities and features required to provide the expected business benefit.