New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 159 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 159 Topic 16 Discussion

PMP Exam Topic 16 Question 159 Discussion:
Question #: 159
Topic #: 16

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?


A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog


B.

Obtain approval from the project team and add the new story to the product backlog


C.

Receive an agreement from the product owner and add the new story to the product backlog


D.

Negotiate with the scrum master before adding the new story to the sprint backlog


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.