PMI Project Management Professional (2025 Version) PMP Question # 146 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 146 Topic 15 Discussion

PMP Exam Topic 15 Question 146 Discussion:
Question #: 146
Topic #: 15

After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?


A.

Log the issue and see if improvements show in the second iteration.


B.

Log the issue and ask a senior member to coach these team members.


C.

Hire new team members to implement the correct way of testing.


D.

Check lessons learned and use the testing process from previous projects.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.