PMI Project Management Professional (2025 Version) PMP Question # 146 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 146 Topic 15 Discussion

PMP Exam Topic 15 Question 146 Discussion:
Question #: 146
Topic #: 15

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?


A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables


B.

Request more funding from the project sponsor to hire additional skilled resources

and to incorporate additional quality in the project delivery approach and outcome


C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions


D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.